Nagpur-Bhandara-Gondia Expressway
Nagpur-Bhandara-Gondia Expressway | |
---|---|
Nagpur-Bhandara-Gondia Access Controlled Super Communication Expressway | |
Route information | |
Maintained by MSRDC | |
Length | 127 km (79 mi) |
Existed | Dec 2024 (expected)–present |
Major junctions | |
West end | Gavasi Village, Nagpur district |
East end | Sawari Village, Gondia district |
Location | |
Country | India |
States | Maharashtra |
Major cities | Nagpur, Kuhi, Bhandara, Tirora,and Gondia |
Highway system | |
The Nagpur-Bhandara-Gondia Expressway, officially named the Nagpur-Bhandara-Gondia Access Controlled Super Communication Expressway, is a planned six to four-lane greenfield project that connects the cities of Vidarbha which are Kuhi, Bhandara, Tirora and Gondia to Mumbai-Nagpur Expressway.[1] Proposed as six to four lanes wide, this segment will reduce the road distance between Nagpur SEZ and Bhandara-Gondia and bring down travel time between Nagpur SEZ and Bhandara-Gondia further to capital of state Mumbai.[2]
Route alignment
The Nagpur-Bhandara-Gondia Expressway will travel through Nagpur, Bhandara, and Gondia districts directly.[3]
Cities and towns
Below are the lists of cities/towns through which the Nagpur-Bhandara-Gondia Expressway will connect:
Construction
MSRDC had applied for Environmental Clearance in October 2023 and invited bids for civil construction in February 2024 with a 2.5 year construction deadline. Bids were opened in early May to reveal 8 firms had submitted a total of 20 bids..:[4]
Sr. No. | Package | Location | Length in km | Contractor | |||||
---|---|---|---|---|---|---|---|---|---|
Code | Chainage in km | Route | Taluka | District | |||||
1. | NG-01 | 0.000 to 29.400 | Gavsi To Chanoda | Nagpur Rural | Nagpur | 29.400 | Afcons Infrastructure Ltd. | ||
Umred | |||||||||
Kuhi | |||||||||
2. | NG-02 | 29.400 to 58.850 | Chanoda to Thana | Kuhi | 29.450 | Afcons Infrastructure Ltd. | |||
Mauda | |||||||||
Bhandara | Bhandara | ||||||||
3. | NG-02A | 58.850 to 94.100 | Thana to Jambhapani | Bhandara | 35.250 | ||||
Mohadi | |||||||||
4. | NG-03 | 94.100 to 121.500 | Manora to Sonegaon | Tirora | Gondia | 27.400 | 31.226 | NCC Ltd. | |
0.000 to 3.826 | Tiroda Connector | Paldongari to Kachewani | 3.826 | ||||||
5. | NG-04 | 121.500 to 144.807 | Sonegaon to Sawari | Tirora | 23.307 | 37.052 | NCC Ltd. | ||
Gondia | |||||||||
0.000 to 13.745 | Gondia Bypass | Lohari to Karanja | Gondia | 13.745 | |||||
Goregaon |
Status updates
This section is empty. You can help by adding to it. |
See also
References
- ^ "Nagpur – Gondia Expressway – Information & Status". 7 July 2024.
- ^ "'Nagpur To Gondia Expressway Project: 8 Firms Play Bids For The Work'". 7 July 2024.
- ^ "'Direct Purchase of Land acquisition for Express Way Nagpur to Gondia, Tahsil-Gondia, Dist-Gondia'". 7 July 2024.
- ^ "'Nagpur – Gondia Expressway: Afcons & NCC Win Contracts'". 7 July 2024.