Kashenyi–Mitooma Road
Kashenyi–Mitooma Road | |
---|---|
Route information | |
Length | 7.7 mi (12.4 km) |
History | Designated in 2017 Completed in 2019 |
Major junctions | |
East end | Kashenyi |
West end | Mitooma |
Location | |
Country | Uganda |
Highway system | |
The Kashenyi–Mitooma Road in the Western Region of Uganda connects the town of Kashenyi in Bushenyi District with the town of Mitooma in Mitooma District. The road measures approximately 12 kilometers (7.5 mi).[1]
Location
The road starts at Kashenyi, about 4.5 kilometers (3 mi) south of Ishaka, on the road to Kagamba, along the Ishaka–Kagamba Road.[2] The coordinates of the road, about 5 kilometers (3 mi) out of Mitooma Town are 0°36'47.0"S 30°04'59.0"E (Latitude:-0.613056; Longitude:30.083056).[3]
Upgrading to bitumen
In 2017, the government of Uganda, hired Chongqing International Construction Corporation (CICO), at a contract price of USh49.199 billion (about US$13.5 million) to upgrade the road from gravel surface to class II bitumen surface and the building of bridges and drainage channels. The contract price included tarmacking of the access road to Katabi Seminary in Bushenyi District, measuring 0.8 kilometers, bringing the total length of the contract project to 12.32 kilometers (7.66 mi).[4][5]
Overview
The tarmacked road is expected to ease transport within the districts of Bushenyi, Mitooma, Rubirizi and Sheema, collectively referred to as Greater Bushenyi. The area is heavily involved in agriculture, both on a subsistence level and increasingly on a commercial level. Agriculture employs nearly 87 percent of the population of the aforementioned districts.[5]
Crops grown in the area on a commercial basis include tea, coffee, matooke, bananas. In addition hybrid cattle are raised in the area for both milk and meat production.[5]
Timeline
Work on the road project started on 31 January 2017. Completion was achieved on 16 January 2019. The one year Defects Liability Period ended in January 2020 and the Uganda National Roads Authority (UNRA) issued a completion certificate to the contractor.[5]
See also
References
- ^ Google (12 December 2020). "Road Distance Between Kashenyi Village, Bushenyi District, Uganda And Mitooma Town, Mitooma District, Uganda" (Map). Google Maps. Google. Retrieved 12 December 2020.
- ^ Google (12 December 2020). "Road Distance Between Kashenyi Village And Ishaka Town" (Map). Google Maps. Google. Retrieved 12 December 2020.
- ^ Google (12 December 2020). "Location of Kashenyi–Mitooma Road" (Map). Google Maps. Google. Retrieved 12 December 2020.
- ^ Conan Businge (8 December 2020). "Museveni to commission Kashenyi-Mitooma-Katabi road". New Vision. Kampala. Retrieved 12 December 2020.
- ^ a b c d Daily Monitor (8 December 2020). "Museveni commissions gateway road to diary-rich Greater Bushenyi". Daily Monitor. Kampala. Retrieved 12 December 2020.
External links
- Compensation Delays Work on Kashenyi-Mitooma Road As of 20 April 2018.
- Uganda National Road Authority Homepage